14 months of hard work in 2 minutes.
It’s exciting to see this landmark 6-storey Angel Storage facility come together in Lidcombe NSW, with strong collaboration across the project team continuing to drive momentum.
With the tower crane now safely dismantled, the team is progressing with the façade glazing, cladding, painting and remaining driveway structure in preparation for the building’s perimeter scaffold removal and weather-proofing structure.
Internally, progress is equally impressive:
- Storage unit fitout is complete on the ground floor and level 1, and progressing rapidly across remaining levels. Each level will be presented with a different roller door colour to identify each level.
- Both level 1 and lower ground ramps structures are advancing, including dividing walls, planter boxes and driveway crossover, in preparation for fencing and landscaping.
- Office and showroom finishing trades have commenced, with service fit off and commissioning scheduled for later this year.
The team is working hard towards completion targeted for early 2027 – Will Anderson, Michael McDermott, Luca Satnarine, Jason De Pass, Nicola Wall.
Read more about the Angel Storage Lidcombe project.