Refurbishment and upgrade of an existing building for self storage fit out
PROJECT DESCRIPTION
Total will commence the demolition of Building B and the refurbishment and upgrade of Building C on an existing industrial site on Parramatta Road, Lidcombe.
Building B will be fully demolished, including asbestos removal.
Building C will have partial demolition of the ground floor and level 1. The ground floor level will be raised approximately 1.4m above the existing level flood zone.
We will construct 98 ground floor storage units and 104 first floor storage units, and provide ground floor car parking for 8 vehicles, pavements and 2 internal car parks on the first floor.
Two additional ground level loading docks will be built and a new car park entry from Day Street.
We will construct a new office and new unisex sanitary facilities on the ground and first floors.
OVERCOMING CHALLENGES
To better suit vehicles movements around the existing and newly constructed loading docks, the boundaries of Building A have been adjusted.
INNOVATIONS
We assisted the client with unit layout optimisation for the best return on investment and suitable office set up.
We’re currently working on design development options for Stage 2 Building A.
Project Contact
Steve is a founding shareholder of Total Construction. Equipped with a carpentry trade background and extensive experience with design and construct projects across all sectors of the building industry, Steve has been a driving force behind the company’s growth and success. With the appointment of a Chairman and CEO, Steve now focuses on the continual development of a successful and sustainable strategy for the business. He also plays a key role in providing leadership for the overall development of the company through strategic marketing, client relationships and procurement. Steve is based in Sydney where he has the overall management in NSW.