Project Update | Precast Installed at BE Campbell
Precast Panels Have Been Installed at BE Campbell
Total Construction has been engaged as Head Contractor for the design and build for the extension for BE Campbell’s pork de-boning facility in Wetherill Park. The project includes upgrades to the facility’s warehouse and cool rooms and construction of a new plant room. BE Campbell have also invested in upgrading staff facilities, including the construction of new amenities, a lunchroom, meeting rooms, PPE Storage rooms and a commercial kitchen for staff to enjoy fresh meals prepared daily.
Over the weekend, 20 precast panels were successfully installed for the new plantroom using a 150T crane, with one of the larger panels weighing up to 13T. The team coordinated with BE Campbell, neighbours and surveyors in the lead up to ensure an effective and safe installation. The team is now preparing for the structural steel to be lifted next week.
The project will enhance the facility’s operations, raising the standards in quality, efficiency and safety of meat production in Australia. Construction is expected to be completed in October 2025.
About BE Campbell
BE Campbell is a family-owned company established in 1969 supplying quality meat products to major supermarkets, restaurants, retail butchers and export markets. They have grown from simple butchering and wholesale into a now vertically integrated supply chain of meat processing, portioning and value-adding retail solutions.
They operate two sites across Western Sydney – a pork de-boning room in Wetherill Park and a multi-species site in Arndell Park. Their Wetherill Park facility can process up to 15,000 pigs a week and has a state-of-the-art SFK deboning system. The Arndell Park site is a value adding meat processing site offering flexible capabilities and retail-ready solutions.
Total Construction's Food & Beverage Group
The Food & Beverage team at Total Construction are highly experienced in the design, engineering and construction of sophisticated food-grade environments. Our depth of knowledge about safety in food-grade environments aligns with BE Campbell’s commitment to meeting the highest standards of hygiene and food safety. The team’s innovative ideas in buildability and methodology for the project, reflecting our strong focus on food safety and compliance, allowed us to secure the project.
Minimising Operational Disruption
With extensive experience in live environment sites, Total Construction understands the importance of effective planning to ensure critical operations can continue during construction. By employing our Early Contractor Involvement (ECI) model and collaborating closely with the client, we can developed tailored solutions that minimise operational disruption to ensure the project is delivered on time and within budget.