Project Update | Kennards Self Storage Chatswood
Project Overview
The team is making excellent progress on the retrofit of the former Westpac Disaster Recovery Centre, transforming the five-storey building into a state-of-the-art Kennards Self Storage facility in Chatswood, NSW.
Delivered under a Construction Management contract, Stage 1 involves converting the existing building into a fit-for-purpose facility that maximises net lettable area and aligns with Kennards’ operational needs and standards.
Located opposite Bunnings, and just a few hundred metres from Kennards’ existing Mann Street location, the site offers outstanding visibility and accessibility. The facility will boast over 400 units and offer an extra 4,000m² of storage space to the area.
The showroom will be separate to the storage space, positioned with high visibility on the Smith St entrance.
The project includes:
- 400 units and an extra 4,000m² of storage space in Stage 1, which will grow to over 10,000m² in later stages.
- A strategic two-phase approach allowing for a quicker initial launch and supporting future scalability.
- Adaptive reuse of the existing structure designed to maximise net lettable area.
- Retrofit of the existing HVAC systems, allowing the existing mechanical air and exhaust systems to be reutilised and upgraded to meet Kennards’ ventilation requirements.
- Upgrade to the fire fighting system including sprinkler system across all levels which is outdated and doesn’t meet the facility’s new purpose.
- Removal of existing in-ground diesel tanks which lie in close proximity to the boundary line retaining wall and the area backfilled.
- An existing onsite above ground OSD tank lies above the diesel tanks and needs to be reinstated to the exact levels as current
- Reinstatement of the existing onsite above ground OSD tank which lies above the diesel tanks.
Construction Update
The team have completed a strategic demolition sequence and are well into the fitout of the storage units, working down from Level 5. With the fitout now 80% complete, the team have commenced external works.