Project Completion | Rocklea Remedial Works
Post date
20.05.2026
Blog Categories
The Queensland delivery team recently completed the remediation of an existing industrial facility in Rocklea, Queensland.
The works included:
- Full replacement of the roof structure and supporting steelwork.
- Temporary works and propping to maintain stability of remaining building elements.
- Full replacement of glulam portal frames.
- Upgrading access systems.
- Major civil remediation with screw piles being tied back to existing footings to stabilise the structure.
The team navigated several challenges, including structural discrepancies identified through as-built surveys and coordination issues between piling and panel clearances, requiring design adjustments.
Tallying over 6,700 hours worked, the project was completed with 0 recordable safety incidents across a high-risk scope.