Project Completion | Beaumont Care, Clontarf QLD
Project Overview
Total Construction successfully completed the refurbishment of a 21-bedroom aged care home for Beaumont Care in Clontarf, Queensland.
The project involved the upgrade of resident bedrooms, ensuites and three decanting rooms within a live operating facility. Delivered across six carefully staged construction phases, the refurbishment was planned and executed to ensure residents continued to receive a safe, comfortable and uninterrupted standard of care throughout the works.
Delivering in a Live Aged Care Environment
Working within an operational aged care facility required detailed planning, stakeholder engagement and flexibility. Construction activities were carefully coordinated around daily facility operations, including mealtimes, personal care routines and resident access requirements.
The project team maintained regular communication with facility management and staff to ensure all works were undertaken with minimal disruption to residents and carers.
Temporary water and electrical shutdowns presented a significant challenge due to the operational requirements of the home. Through proactive scheduling and detailed planning, these activities were conducted around kitchen operations and resident care routines, preventing unexpected interruptions and helping maintain a calm and supportive environment.
Innovations
A key project innovation involved consolidating Stages 5 and 6 within the same segregated wing of the facility. This strategic approach reduced the overall programme duration, improved construction efficiencies and minimised the frequency of disruption to residents and staff.
By adapting the staging methodology, the team was able to streamline delivery while maintaining safety and operational continuity.
Overcoming Challenges
The refurbishment presented several complexities, including existing mould conditions that required additional investigation and coordination as the project progressed.
Material procurement challenges, lead time pressures and occasional fixture performance issues also required careful management to maintain programme objectives. Through strong collaboration with consultants, subcontractors and the client team, these challenges were effectively resolved while maintaining quality standards.
Project Outcomes
The completed refurbishment has delivered a significant upgrade to resident accommodation, improving both the functionality and presentation of bedrooms and ensuites while enhancing the living environment for residents.
The project was successfully completed in just 40 weeks and achieved outstanding safety outcomes:
- 21 refurbished resident bedrooms and ensuites
- Three refurbished decanting rooms
- Completed within a live operating aged care environment
- Delivered in 40 weeks
- Zero Lost Time Injuries
- Zero Notifiable Incidents
Our team at Total Construction understands the unique challenges of delivering projects within live health care and aged care environments. Through careful planning, collaboration and a commitment to resident wellbeing, we create spaces that support better outcomes for providers, staff and the communities they serve.