Construction of an extension, hydrotherapy pool and car parking facilities.

PROJECT DESCRIPTION

Total Construction worked very closely with Healthe Care to achieve a negotiated outcome, and deliver a high-quality finished product which aligned with budget requirements.

The project involved two stages with contrasting work areas/frontages to be completed concurrently.

The main stage of works was the demolition of existing consulting suites and hydrotherapy pool and the construction of a new extension. This extension comprises 10 single bed wards, three double-bed wards, reception and administration areas, pathology suite and a base build for a doctor’s consultancy suite. This suite was later fitted out as part of a separate contract with the tenant doctor.

Stage 2 of the works involved the refurbishment of an existing part of the hospital to construct a new rehabilitation area, including a hydrotherapy pool, gymnasium and changing rooms.

OVERCOMING CHALLENGES

While excavating the pool, we discovered insufficient foundations surrounding the building which delayed pool construction as we waited for engineering and underpinning to take place.

Most of the works consisted of a straightforward fit-out, however, where old walls were demolished there was a variety of different floor levels which resulted in a significant amount of floor levelling to provide a suitable area for rehabilitation patients to walk.

Project Contact

Jeff Jones
CEO / (Interim) General Manager VIC

Originally from a financial executive perspective and now as CEO, Jeff has broad industry experience across the construction, engineering and property development market segments. Leveraging his skills obtained from becoming a Chartered Accountant and completing an MBA, Jeff is responsible for the leadership and operational performance management of the company within the strategy and business plan agreed by the Board.

`