Project Specifications
Extension of chilled water piping from under Broadway into the UTS building.
PROJECT DESCRIPTION
Total Construction was asked to install and commission an energy transfer station in UTS to link the Central Park CTP to the UTS Central Energy Plant.
Directional drilling was undertaken to allow pipe installation from Jones Street through to UTS building 02. We also installed and pressure-tested the HDPE pipe. This pipe transports chilled water to the building and used for cooling.
OVERCOMING CHALLENGES
We were working in a live environment with students and the general public. Safety was of the utmost importance as was reducing noise levels so as not to interrupt student exams.
INNOVATIONS
Our client had the benefit of our knowledge of the existing Central Park plant and the experience in implementing the energy transfer systems. This resulted in a rapid design development phase.
Project Contact
Steve is a founding shareholder of Total Construction. Equipped with a carpentry trade background and extensive experience with design and construct projects across all sectors of the building industry, Steve has been a driving force behind the company’s growth and success. With the appointment of a Chairman and CEO, Steve now focuses on the continual development of a successful and sustainable strategy for the business. He also plays a key role in providing leadership for the overall development of the company through strategic marketing, client relationships and procurement. Steve is based in Sydney where he has the overall management in NSW.